Residential Demolition Specifications: What a House Teardown Spec Covers
Residential demolition specifications spell out which structures on a lot are to be demolished and exactly what the contractor shall remove. They also say how the lot has to look when the crew leaves. It's the written scope a crew prices against. If a line is vague, two bids on the same house can describe two very different jobs.
Specs usually come as a PDF, sometimes tucked inside a bigger construction plan set. Here's how a crew reads one for a Treasure Valley house teardown, and which lines move the price.
What goes into residential demolition specifications?
They cover five things: what comes down, how utilities get shut off, how much foundation goes, where demolition debris ends up and how the lot is left. The schedule, the safety notes and the price all hang off those five.
1. The scope: which designated structures are to be demolished
The scope names the designated building structures that are coming down. On a home lot that might be the house, a detached garage, a shed, a carport, a deck or an old pool.
Be specific. "Remove all structures" sounds clear until someone asks about a shared fence or the slab under the shed.
A short list in the PDF works better than a sentence:
- House, including attached garage and porches
- Detached garage and its slab
- Backyard shed on blocks
- Rear deck and stairs
Taking down one thing and keeping the rest is selective demolition. The spec should mark the line, mainly where something attaches to a part that stays.
2. Utility disconnects and capping before work starts
Utility lines get disconnected and capped before demolition work starts. The spec should say who handles each one. The utility companies usually shut off power and gas. Water and sewer are often capped at the property line or the main. It depends on what the city wants.
Why does it matter? Nothing comes down safely with live lines in it. Cities often want disconnects done before they sign off on a demolition permit.
Heads up: "Contractor to coordinate utility disconnects" isn't the same as "contractor to pay for them." If the spec doesn't say who covers the sewer cap, ask before you sign.
3. Foundations, slabs, footings and flatwork
This section often moves the price more than any other. The spec has to say how deep the foundation comes out. Is it all of it, footings included? Or only to a set depth below grade?
Full removal means more digging, more concrete to haul and more fill coming back in. Leaving footings in place can make sense if you're building on the same footprint. But it affects the new construction, so your builder or engineer should make that call, not the demo crew.
Flatwork belongs here too: driveways, sidewalks, patios and garage slabs. The spec should list which ones go and which stay.
4. Debris handling, salvage, recycling and donation
This section says where debris goes and what gets set aside first. Clean concrete, metal and some lumber can be recycled instead of buried at the Ada County landfill. Usable material can sometimes be donated. Want recycling receipts? Ask for them in the PDF.
Want to keep something, like garden pavers or old brick? Take it before the crew shows up, or put it in the spec. If not, it goes with everything else.
5. Backfill, grading and how the site is left
The last section covers what happens to the hole. A basement or crawlspace has to be backfilled. The spec should say what fills it: clean fill, native soil, or compacted fill for new construction. It should also say how the site is graded at the end.
"Leave site clean" isn't a finish spec. Rough graded and level? Graded to drain away from the neighbors? Seeded? Each one is a different amount of work. A grading plan from your builder, added to the PDF, settles it.
What "the contractor shall remove" really commits a crew to
"The contractor shall remove" commits the crew to everything listed after those words, and nothing more. A crew prices what's written, not what you had in mind.
When the spec says "entire building"
"Entire building" usually means everything above grade plus the foundation, unless the spec says otherwise. It doesn't include the detached garage, the shed or the driveway unless they're listed.
Want the whole lot cleared? Say so. Want the house gone but the garage kept for storage during your build? Say that too.
What stays unless the spec says otherwise: trees, fences, driveways, neighboring structures
Anything not listed usually stays. That tends to include:
- Trees and landscaping
- Fences, especially on a property line
- Driveways and approaches to the street
- City sidewalks and curbs
- Anything on a neighboring lot
On older lots in the North End or on the Bench, big shade trees often sit close to the house. Their roots can wrap around footings. If a tree stays, the spec should say how it'll be protected during demolition work.
Good to know: Lots near the Boise River or a creek can have riparian setbacks. They limit where equipment can go near the bank. Check with the city before the demolition plan is set.
Vague lines that change the price, and how to tighten them
These are the lines that cause the most back-and-forth at an estimate.
| Vague line | Tighter version |
|---|---|
| Remove all structures | Remove house, detached garage and shed, each listed by location |
| Remove foundation | Remove foundation and footings completely |
| Cap utilities | Contractor caps water and sewer at property line; owner arranges power and gas shutoff |
| Clean up site | Backfill with clean fill, compact, rough grade to drain |
| Salvage as directed | Owner removes garden pavers and mailbox before work starts |
| Haul debris | Recycle clean concrete and metal; dump tickets go in the closeout PDF |
| Control dust | Wet down the structure and debris as work goes |
Demolition dust earns a line of its own. In a hot, dry Boise summer it travels, and neighbors notice. Wetting things down is the usual way to keep it in check.
Worth asking: When the crew walks the lot, ask them to discuss condition of anything that's staying, like the sidewalk, the curb and the neighbor's fence. Photos taken before work starts, saved to the PDF, make it easy to discuss condition again at the end.
What are the general specifications for a residential building?
The general specifications for a residential building are the shared rules for the whole project. They cover local building regulations, working hours, safety, cleanup and how changes get approved. Technical specifications then cover each trade's work, demolition included.
In a teardown spec, the general section usually covers:
- Who pulls the permit and when
- The demolition schedule and working hours
- Construction fencing, safety rules and emergency contacts
- How changes to the scope get approved
- An EHS section on bigger construction jobs, covering health and environmental rules
Something can turn up mid-job, like an old buried fuel tank or a slab nobody knew about. The spec should say how it's priced and approved before work keeps going.
How construction specs number a teardown
Demolition sits in Division 02, Existing Conditions, in the CSI numbering architects and builders use. Section 02 41 00 covers it, with whole-structure and partial work broken out under it.
A house teardown PDF uses the same bones as a commercial one, just shorter. The headings help you catch what's missing.
Why the spec should go out as one PDF
One PDF means every crew bids the same job. A good one has:
- A cover page with a date, so everyone knows which version is current
- Each structure coming down, plus the items that stay
- The asbestos survey, if you have one
- Your builder's grading plan
- Any city forms
Changed the scope? Send a new, dated PDF.
Frequently asked questions about teardown specs
Is there a residential demolition specifications PDF I can use?
Free PDF templates are out there, but many are written for commercial projects. Use one as a checklist and cut it down to fit your lot.
Who writes the specs for a house teardown?
Usually the architect, builder or owner. On a simple teardown, the contractor often helps write the scope at the estimate.
What should be inspected before the spec is final?
Walk the whole lot, check for asbestos and other hazardous materials, and find the utilities. Call 811 before any digging. Ask the city whether it wants an asbestos survey filed first.
Does the spec need to say what happens to a basement, pool or septic tank?
Yes. Each one needs its own line: removed or filled, with what, and who signs off. Septic tanks usually go through the local health district.
Getting a teardown spec that prices cleanly
A clear spec makes for a clear price, and it gets you bids you can actually compare, even if you go another way.
Boise Demolition does whole-structure and exterior demolition across the Treasure Valley, from Eagle and Star to Meridian, Nampa, Caldwell and Kuna. Every job starts with a free on-site estimate and a firm price before anything is touched.
The Residential Demolition Services page covers what the service includes and how the estimate works.
Related reading: Residential Demolition Notes: What They Say and Why They Matter and Residential Demolition Costs: What Really Sets the Price on a Teardown.
Related reading: Residential Demolition Notes: What They Say and Why They Matter and Residential Demolition Costs: What Really Sets the Price on a Teardown.
Got a spec, or just a lot and a plan? Call us at (208) 296-6153.
Planning a Demolition Project?
We handle permits as part of our demolition services throughout Boise, Meridian, Nampa, and the Treasure Valley. Call for a free estimate.
Call (208) 296-6153More From Our Blog
Demolition Labor Cost per Hour vs. Total Demolition Cost on a Teardown
Demolition labor cost per hour tells you little about a teardown. Learn what really drives house demolition costs and why crews price by the job.
Demolishing a Garage: How It Comes Down, Slab and All
Demolishing a garage, step by step: utilities and permits, attached vs. detached, block walls, slab removal and when an old roof needs asbestos testing.
Do I Need a Permit for Building Demolition? Who Handles What
Do I need a permit for building demolition? Usually, yes. Here's what comes before the application, who handles each step and what moves the cost.